Construction Planning and Management MCQs

26. In resources levelling________________?

A. total duration of project is reduced
B. total duration of project is increased
C. uniform demand of resources is achieved
D. cost of project is controlled
✅ The correct answer is option C.

30. Latest start of an activity is always________________?

A. greater than or equal to latest event time of preceding node
B. less than or equal to latest event time of preceding node
C. equal to latest event time of preceding node
D. less than latest event time of preceding node
✅ The correct answer is option A.