Prepare with the best Chemical Engineering MCQs with answers and detailed explanations for exams and job tests. Our collection covers key topics such as chemical process calculations, thermodynamics, fluid mechanics, heat transfer, mass transfer, reaction engineering, instrumentation, and plant design. These Chemical Engineering multiple-choice questions are ideal for students, competitive exam aspirants, and professionals preparing for NTS, PPSC, FPSC, PEC exams, GATE, university entry tests, and job interviews. Practice online with updated Chemical Engineering MCQs to strengthen your concepts and improve technical problem-solving skills.

434. On-off control

A. Fully opens the final control element, when the measured variable is below the set point
B. Fully closes the final control element, when the measured variable is above the set point
C. Is a two position control (fully open or fully closed) control adequate to control a process with slow reaction and minimum dead time or transfer lag
D. None of these
✅ The correct answer is option C.
Scroll to Top