21. A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
Ratio of times taken by A and B = 100 : 130 = 10 : 13.
Suppose B takes x days to do the work.
Then, 10 : 13 :: 23 : x x =
23 x 13
x =
299
.
10
10
A’s 1 day’s work =
1
;
23
B’s 1 day’s work =
10
.
299
(A + B)’s 1 day’s work =
1
+
10
=
23
=
1
.
23
299
299
13
Therefore, A and B together can complete the work in 13 days.