✅ The correct answer is option B. 10 days.
Work done by X in 4 days = ( 1/20X 4 ) = 1/5 Remaining work = (1 – 1/5 ) = 4/5 (X + Y)’s 1 day’s work = 1/20 + 1/12 = 8/60 = 2/15 Now, 2/15 work is done by X and Y in 1 day. So, 4/5 work will be done by X and Y in 15/2 X 4/5 = 6 days Hence, total time taken = (6 + 4) days = 10 days.
✅ The correct answer is option C. 285 cm2.
Area of a trapezium = 1/2 (sum of parallel sides) * (perpendicular distance between them) = 1/2 (20 + 18) * (15) = 285 cm2