[A]. 8 days
[B]. 10 days
[C]. 12 days
[D]. 15 days
✅ The correct answer is option C.
(A + B)’s 1 day’s work =
(A + B)’s 1 day’s work =
1
+
1
=
1
.
15
10
6
Work done by A and B in 2 days =
1
x 2
=
1
.
6
3
Remaining work =
1 –
1
=
2
.
3
3
Now,
1
work is done by A in 1 day.
15
2
work will be done by a in
15 x
2
= 10 days.
3
3
Hence, the total time taken = (10 + 2) = 12 days.