15412. A technique for performing quantitative analysis of progress is known as______________________?

A. BCWS
B. EVA
C. BAC
D. CBSE
✅ The correct answer is option B.
Explanation: The earned value system provides a common value scale for every task, regardless of the type of work being performed. The total hours to do the whole project are estimated, and every task is given an earned value based on its estimated percentage of the total.