HomeEngineeringIf the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________? 899. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________?By Admin / September 7, 2025 A. 50% B. less than 50% C. more than 50% D. 100% ✅ The correct answer is option C.