878. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is__________________? September 7, 2025 by Admin A. 8 days B. 9 days C. 10 days D. 15 days ✅ The correct answer is option B.